TL;DR: Liquidated damages are a fair sum agreed at signing to cover a likely loss, and courts usually enforce them. A penalty is a sum set to punish, and US courts treat an unreasonably large one as void. Once your clause is ready, our contract signing software keeps the signed copy and its record in one place.
A supplier promises to deliver parts by the first of the month. Each late day stops the buyer’s line and costs real money. Both sides want to agree the cost of a late day now, before anything goes wrong.
A damages clause handles this. Set the figure fairly and a court will usually uphold it. Set it to punish and the clause can fail just when you need it.
This guide is general information, not legal advice. Contract law differs by country and state, so ask a lawyer about your own contract.
What are liquidated damages?
Liquidated damages are a fixed sum, or a set formula, that one side pays the other after a breach. The parties agree the figure in the contract before the breach happens.
Think of a deposit on a hotel booking. The hotel keeps a set amount if you cancel late, because it may not rebook the room. Nobody argues later about what the empty night really cost.
Cornell Law School’s definition of liquidated damages says parties use them where real losses are hard or impossible to prove. The clause saves both sides the time and cost of proving the loss in court.
What is a penalty clause in a contract?
A penalty clause sets damages that are unreasonably high and act as punishment for a breach. It is not a fair forecast of the harm the breach causes.
Cornell’s penalty clause entry gives a clear example.
A lease charges 1,000 dollars a month in rent. It then asks a tenant who stays on past the end date to pay 750 dollars a day. That daily charge is far above the real loss, so it reads as a penalty.
Courts generally enforce liquidated damages but do not enforce penalties. The question is always which side of that line your figure falls on.
What is the difference between liquidated damages and a penalty?
The difference is purpose. Liquidated damages aim to compensate, while a penalty aims to punish or scare the other side into performing.
| Point | Liquidated damages | Penalty |
|---|---|---|
| Purpose | Covers a likely loss | Punishes a breach |
| How the figure is set | From an estimate of real harm | High enough to scare |
| Link to actual loss | Close and explained | Weak or missing |
| Usual result in a US court | Enforced when reasonable | Void as a penalty |
Both kinds of clause look alike on the page. Each names a sum that falls due after a breach, so the test sits in how the figure was chosen.
How do US courts decide if a damages clause is valid?
US courts ask whether the amount is reasonable. A term that fixes an unreasonably large sum is void as a penalty.
The rule for sales of goods
The Uniform Commercial Code (UCC) covers contracts for the sale of goods in the US. UCC section 2-718(1) allows damages to be liquidated at a reasonable amount. It weighs reasonableness against these points:
- The harm the breach was expected to cause, or did cause
- How hard it would be to prove the loss
- How hard it would be to get a fair remedy another way
The rule for other contracts
Many other contracts follow the Restatement (Second) of Contracts, a summary of common law that courts often cite. Its section 356, quoted in Cornell’s penalty clause entry, uses a similar test. The amount must be reasonable given the expected or actual loss and how hard that loss is to prove.
Each state applies its own version of these rules. Your lawyer can tell you which one governs your contract.
How do other countries treat damages clauses?
Other countries set their own tests. The UK, India and Kenya, for example, each have their own rules and court decisions on damages clauses.
A clause that works under one country’s law may be read differently under another. Name the governing law in the contract, and have a lawyer from that country check the clause.
How do you draft an enforceable liquidated damages clause?
Start from the real loss, not from the figure that sounds tough. These steps follow the US reasonableness test:
- List the losses a breach would cause, such as lost rent or downtime.
- Estimate each loss at the time you sign, with your sources.
- Set the sum, or a daily rate, close to that estimate.
- Explain in the clause why the loss would be hard to prove later.
- Keep your workings with the signed contract.
What does a sample clause look like?
Here are two short clauses for a late delivery. Treat them as illustrations, and ask a lawyer to adapt the wording.
“If delivery is late, the Supplier will pay the Buyer 15,000 dollars for each day of delay. The parties agree this sum is a fair estimate of the Buyer’s daily downtime cost, which would be hard to prove after a breach.”
“If delivery is late, the Supplier will pay 100,000 dollars a day as a penalty.”
The first clause ties the sum to a stated loss and gives a reason. The second gives no link to any loss and names itself a penalty, so a court is likely to question it.
What mistakes turn a damages clause into a penalty?
Most failed clauses share a few habits. Watch for these when you draft or review one:
- A figure many times larger than any likely loss
- Words such as “fine” or “penalty” in the clause
- No record of how the figure was worked out
- The same flat sum for small and large breaches
- An old figure that no longer matches today’s costs
Review your standard clauses each year. Costs change, and a fair figure from five years ago may look too high today.
How do you get a damages clause signed and on record with BoldSign?
A damages clause helps only if you can show what both sides signed. We keep each signed document in your BoldSign account.
Every document you send gets an audit trail. It records who signed and the time of signing.
The audit trail also logs the device and how each signer was verified. You get it as one PDF with the signed document.
For contracts you send often, save the document as a reusable template. Your reviewed damages wording then stays the same on every send.
Which BoldSign plan do you need, and what does it cost?
Signing and the audit trail come with every plan. The number of templates is what changes between plans.
The Essential plan is free and includes 2 templates. The Growth plan costs $5 per user a month and includes 10 templates.
The Business plan costs $15 per user a month with unlimited templates. The Premium plan costs $99 a month for unlimited users, with unlimited templates.
Prices are in USD and billed yearly, as listed on our pricing page in November 2026.
What should you do before you sign your next contract?
Check that every damages figure in the contract links to a real loss. Then pick your next step:
- Start a 30-day free trial of BoldSign
- Book a demo to see contract signing with your own documents
- Ask our team a question on the support portal
Frequently asked questions
What is the main difference between liquidated damages and a penalty?
Liquidated damages are a fair estimate, made at signing, of the loss a breach would cause. A penalty is a sum set high to punish or scare the other side, with little link to real loss.
Are liquidated damages clauses enforceable?
Yes, when the amount is reasonable compared with the likely or actual harm and the loss is hard to prove. In the US, a clause with an unreasonably large amount is treated as a penalty.
Are penalty clauses legal in a contract?
Yes, when the sum is a fair estimate of loss, because US courts then treat it as liquidated damages whatever its name. An unreasonably large sum is void as a penalty. Other countries use their own tests.
Can a court change the amount in a damages clause?
It depends on the law of the contract. Under the US rules, an unreasonably large damages term is void as a penalty, so you may be left to prove your actual loss instead.
Is a clause labelled liquidated damages valid?
Yes, when the amount is also reasonable. The US tests look at the figure and the harm, so the heading alone does not decide the outcome.
What is an example of a liquidated damages clause?
A supply contract might say the seller pays a set daily sum for each day of late delivery. The sum should match the buyer's expected cost of each lost day, worked out before signing.
Is a liquidated damages clause valid in an electronically signed contract?
Yes, when the clause itself is valid and both sides agreed to sign electronically. The way a contract is signed does not change the test a court applies to the clause.
Should a lawyer review my liquidated damages clause?
Yes, for any clause with real money at stake. A lawyer can check the amount against the law that governs your contract and help you record how you set it.